Sh. Ashish Kush, Planning Executive and Ms. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Abhijeet Singh, CEO, Sh. Manik Sharma (AR) and Sh. Bharat Vigmal (AR) are present on behalf of the promoter. Approved as proposed subject to submission of DD/BG of Rs. 25 lakhs each as a security amount for submission of Approved service plan estimates, Fire scheme approval and EC within four months. The AR further states that the construction will be completed and OC obtained within six years while completion of the project including all the amenities shall be completed within the date specified in the DPI. The road access permission will be submitted within three months and condition to this effect will be incorporated in the RC.
- Home
- RERA Projects
- Gurugram
- M3m Mansion
GGM/802/534/2024/29
RERA overview
As filed by the promoter in Form REP-I with HRERA Gurugram.
- businessPromoter
- Union Buildmart Private Limited
- placeLocation
- Village Chauma,Sector 113,Gurugram
- mapTehsil / District
- Gurgaon, Gurugram
- verifiedRERA status
- Approved and certificate uploaded
- account_balanceAuthority
- HRERA Gurugram
- edit_calendarApplied on
- 21 Feb 2024
- architectureLayout plan approved
- 20 Feb 2024
- constructionConstruction start
- 01 Mar 2024
- event_availableCompletion date
- 29 Feb 2032
- workspace_premiumRegistration valid
- 18 Mar 2024 – 31 Mar 2030
- layersFAR (permissible / proposed)
- 3.99 / 3.94
- paymentsEstimated project cost
- ₹ 2,332.98 Cr
Licence
Land use 8.71 acres in all
Estimated cost ₹ 2,332.98 Cr in all
Promoter
- Company
- Union Buildmart Private Limited
- Registered office
- 41st Floor, Tower-1, M3M International Financial Center, Sector-66, Badshahpur, Gurgaon, Haryana
- CIN
- U70100HR2012PTC089615
Book a free site visit
Latest price, offers and a guided visit of M3m Mansion.
Mr Prashant Agarwal is available to discuss all your queries.
Online now · replies on WhatsApp
Quick questions
Plot sizes
1 sizes · 0 plots registered with RERA. Tap a column to sort.
| Sq yd | Sq ft | Sq m | Plots |
|---|---|---|---|
| 0 | 0 | 0 | 0 |
Areas are as registered with RERA (square metres); square yards and square feet are converted. Final sizes are as per the allotment.
Unit types
968 units in 1 types as registered with RERA.
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Apartment/Shops/Other Buildings | 1,825 – 13,66,257 | 968 |
Carpet areas as filed with RERA (square metres, shown in square feet). Booked / unsold are as on the RERA application date.
Facilities & services
18 facilities in the promoter's service plan estimate · ₹ 98.37 Cr budgeted.
-
add_road
Internal Roads and Pavements ₹ 7.65 Cr est.
-
water_drop
Water Supply System ₹ 2.12 Cr est.
-
water
Storm Water Drainage ₹ 91.85 L est.
-
bolt
Electricity Supply System ₹ 7.04 Cr est.
-
recycling
Sewage Treatment & Garbage Disposal ₹ 1.53 Cr est.
-
light
Street Lighting ₹ 61.23 L est.
-
local_fire_department
Security and Fire Fighting ₹ 3.93 Cr est.
-
park
Playgrounds and Parks ₹ 91.85 L est.
-
nature
Hardscape and Softscape ₹ 18.68 Cr est.
-
fence
Boundary Wall ₹ 6.43 Cr est.
-
security
Guard House ₹ 3.06 Cr est.
-
local_parking
Parking ₹ 2.5 Cr est.
-
recycling
Sewage Treatment Plant (STP) ₹ 1.97 Cr est.
-
water_drop
Underground Water Tank ₹ 2.35 Cr est.
-
water_drop
Rain Water Harvesting ₹ 15.31 L est.
-
bolt
Electrical Sub Station ₹ 10.11 Cr est.
-
bolt
Electrification Till Site ₹ 14.01 Cr est.
-
check_circle
Infra Establishment ₹ 6.12 Cr est.
Also budgeted Consultancy · ₹ 8.27 Cr
Not in this filing Club House / Community Centre Shopping Area Renewable Energy System School Hospital / Dispensary
External connections
- radio_button_uncheckedRoads GMDA
- check_circleWater Supply GMDA
- check_circleElectricity DHBVN
- check_circleSewage Disposal GMDA
- check_circleStorm Water Drainage GMDA
Specifications
- Flooring Details of Various Parts of House
- VITRIFIED TILES/LAMINATEDWOODEN FLOOR/CERAMIC TILE
- Wall Finishing Details
- PLASTER WITH OBD
- Kitchen Details
- N.A.
- Bathroom Fittings
- N.A.
- Wood Work Etc
- N.A.
- Doors and Windos Frames
- EXTERNAL ALUMINIUM WITH GLASSINTERNAL – WOODEN
- Glass Work
- ONLY EXTERNAL DOOR/WINDOW
- Electric Fittings
- AS PER APPROVED MAKE
- Conducting and Wiring Details
- AS PER APPROVED MAKE
- Cupboard Details
- N.A.
- Water Storage
- AS PER NORMS
- Lift Details
- LIFTS AS PER BUILDING PLANS
- External Glazings
- GLASS WITH ALUMINIUM FRAMINGSLIDING
- Windows / Glazings
- GLASS WITH ALUMINIUM FRAMINGSLIDING
- Main Doors
- HARD WOOD DOOR FRAME WITHFLUSH DOOR /LAMINATE
- Internal Doors
- HARD WOOD DOOR FRAME WITHFLUSH DOOR /LAMINATE
- Electrical Fittings
- AS PER APPROVED MAKE
- Cng Pipe Line
- N.A.
- Provision of Wifi and Broadband Facility
- N.A.
- External Finishing / Colour Scheme
- WATER PROOF PAINT
- Internal Finishing
- PAINT/GLASS
- Floor
- VITRIFIED TILES
- Walls
- PLASTER OBD
- Ceiling
- OBD
- Floor
- VITRIFIED TILES/LAMINATE WOODEN FLOORING
- Walls
- PLASTER & OBD
- Ceiling
- OBD
- Modular Wardrobes
- N.A.
- Floor
- ANTISKID CERAMIC TILES
- Walls
- PLASTER & DADO
- Ceiling
- GRID FALSE CEILING/OBD
- Counters
- N.A.
- Sanitary Ware / Cp Fittings
- AS PER APPROVED MAKE
- Fitting / Fixtures
- AS PER APPROVED MAKE
- Floor
- VITRIFIED TILES/LAMINATE WOODEN FLOORING
- Walls
- PLASTER & OBD
- Ceiling
- OBD
- Wardrobes
- N.A.
- Floor
- ANTISKID CERAMIC TILES
- Walls
- PLASTER & DADO
- Ceiling
- GRID FALSE CEILING/OBD
- Counters
- N.A.
- Sanitary Ware / Cp Fittings
- AS PER APPROVED MAKE
- Fixtures
- AS PER APPROVED MAKE
- Floor
- VITRIFIED TILES
- Walls
- PLASTER & DADO
- Ceiling
- OBD
- Counters
- STONE/MARBLE
- Fixtures
- AS PER APPROVED MAKE
- Kitchen Appliances
- N.A.
- Floor
- ANTISKID VITRIFIED TILES
- Walls & Ceiling
- PLASTER & PAINT
- Toilet
- ANTISKID CERAMIC TILES
- Balcony
- ANTISKID CERAMIC TILES
- Floor
- N.A.
- Walls & Ceiling
- N.A.
- Railings
- N.A.
- Fixtures
- N.A.
Statutory approvals
Approvals declared in Form REP-I Part E.
- verified License Approval Obtained
- verified LOI Approval Obtained
Plans filed with RERA
- check_circleLayout plan
- check_circleDemarcation plan
- check_circleZoning plan
- check_circleBuilding plan
- check_circleSite plan
- check_circleFloor plan
- check_circleApartment plans
- check_circleElevation section
- check_circleDetail of permissible FAR
- check_circleDetail of covered area achieved FAR
- check_circleRoads and pavement plan
- check_circleElectricity supply plan
- check_circleWater supply plan
- check_circleSewerage and garbage disposal plan
- check_circleStorm water drainage
- check_circleStreet lighting plan
- check_circleParking plan
RERA documents
109 documents downloaded from the HRERA portal. Opens as PDF.
Plans & layouts
Licence & approvals
CA certificates
Financials
Declarations
Other documents
Hearings & orders
Proceedings recorded by the Authority on this registration.
Development schedule
Planned spend each year, from the promoter's quarterly schedule.
Completion committed to RERA: 29 Feb 2032.